Project Name

Firestone Trading Pvt. Ltd

Location: Karjat, Ahmednagar
Capacity: 5.247 MW
Service Type: Operation and Maintenance
Highlights:

We have been awarded this O&M contract in May 2017.
After taking up this O&M Contract, we have upgraded this project to get the optimum power generation from 5.247 MW plant. We faced many challenges like transmission lines, panels upgradation, transformer maintenance, important parts replacement. Now this project is flaw less and working in very good manners.




Project Name

Amazon Warehouse, Bhiwandi

Location: Amazon Warehouse, Bhiwandi
Capacity: 1 MW
Service Type: Operation and Maintenance
Completion: 6 Weeks
Highlights:

We have been awarded this O & M contract in January 2020. After taking up this O & M Contract, we have upgraded this project to get the optimum power generation from 1 MW plant. We faced many challenges like transmission lines, panels upgradation, transformer maintenance, important parts replacement. Now this project is flaw less and working in very good manners.






Project Name

Bhave Warehousing & Cold Storages Pvt Ltd

Location: Taloja, Navi Mumbai
Capacity: 140 KW
Completion: 6 Weeks
Savings: 2 lac per month
Highlights:

Payback rates of commercial warehouses in the state are highest.
GWRE designed and installed 140 KW system for the warehouse.
REC twin peak solar panels of 345 watt each were used in the project which is one of premium quality panels recognised globally

The set up has saved them approximately 2 lac rupees per month. Commissioning Date 27-05-2018




Project Name

Gurudwara, Kharghar, Navi Mumbai

Location: Kharghar Gurudwara, Navi Mumbai
Capacity: 49 kw
Completion: 5 Weeks
Daily units generation approx: 196
Yearly units generation: 71540
Yearly Saving: 12,16,180/-
Highlights:

First Gurudwara to Get Solar Electrified in Navi Mumbai.




Project Name

Mahavir Amrut Co.op Housing Society

Location: Sanpada, Navi Mumbai
Capacity: 42 kw
Completion: 50 Days
Daily units generation approx: 168 Units
Yearly units generation: 61320 Units
Yearly Saving: 8,58,480/-



Project Name

Wadhwa Atmosphere

Location: Wadhwa Atmosphere, Mulund
Capacity: 40 KW
Completion: 45 Days
Daily units generation approx: 160 Units
Yearly units generation: 56960 Units
Yearly Saving: 7,97,440/-



Project Name

Saki Heritage Co. Op. Housing Society

Location: Andheri East
Capacity: 17 kw
Completion: 45 Days
Daily units generation approx: 68 Units
Yearly units generation: 24820 Units
Yearly Saving: 3,47,480/-



Project Name

Petrol Pump, Dhule

Location: Petrol Pump, Dhule
Capacity: 10KW
Type : Off Grid
Completion: 6 Weeks
Daily units generation approx: 40
Yearly units generation: 14,600 Units
Yearly Saving: 1,75,200/-
Highlights:

Payback rates of petrol pump in the state are highest. GWRE designed and installed 10 KW system for the petrol Pump. REC twin peak solar panels of 330watt each were used in the project which is one of premium quality panels recognised globally
The set up has saved them approximately Rs. 14,400 per month. Commissioning Date 28 Dec 2019




Project Type

Bungalow

Location: Kharghar
Capacity: 5 kw
Completion: 45 Days
Daily units generation approx: 20 Units
Yearly units generation: 7300 Units
Yearly Saving: 1,02,200/-